An Ordinance authorizing the City Manager to execute Supplemental Agreements with Bacon Farmer Workman Engineering & Testing, Inc., for the design of sidewalks along North Cape Rock Drive, in the City of Cape Girardeau, Missouri.



EXECUTIVE SUMMARY

The Supplemental Agreements between the City of Cape Girardeau and Bacon Farmer Workman Engineering & Testing, Inc., update delivery milestones and expanding the cost of work specified in the Engineering Services Contract and Program Agreement for the design of sidewalks along N. Cape Rock Drive.



BACKGROUND/DISCUSSION
The scope of work in the ESC was changed in the ESC Supplemental Agreements (021) and (022) due to needs discovered once design work in the field began. Due to the need for acquisition of easements along the project, we are revising the original PS&E approval deadline dates and the cost of work

FINANCIAL IMPACT
The changes will effect on the costs and services to be provided under the provisions of the agreement.

SUSTAINABILITY: ECONOMIC, ENVIRONMENTAL AND SOCIAL IMPACTS


STAFF RECOMMENDATION
Staff recommends Council approve an ordinance authorizing the City Manager to enter into a Supplemental Agreements between the City of Cape Girardeau and Bacon Farmer Workman Engineering & Testing, Inc., updating delivery milestones and expanding the cost of work specified in the Engineering Services Contract and Program Agreement for the design of sidewalks along N. Cape Rock Drive, contingent upon MoDOT approval.

BOARD OR COMMISSION RECOMMENDATION


PUBLIC OUTREACH